Client Portal

/Overview
AN

Client Portal

Kilbarry Rd 88

Raj & Priya Mehta

Active
0%

$47,500

Contract

$32,300

Spent

18

Days Left

Milestones

MobilizationJan 20
FramingJan 27 - Feb 14
Spray Foam InsulationFeb 17 - 21
Drywall InstallationFeb 24 - Mar 10
Taping & MuddingMar 11 - 24
55%
Sanding & FinishingMar 25 - Apr 2
Punch List & HandoffApr 3 - 7

Invoices

InvoiceDescriptionAmountStatusAction
INV-041Mobilization & materials$11,875Paid
INV-044Framing & spray foam complete$14,250Paid
INV-047Drywall & taping progress$14,250Sent
INV-050Final balance + holdback$7,125Draft

Messages

4 messages
Second coat of mud is done on the basement. Moving to main floor tomorrow.
TheSix·Mar 15, 4:45 PM
Looks great so far. Will the sanding create a lot of dust upstairs?
Raj Mehta·Mar 16, 9:10 AM
We use dustless sanders and hang poly barriers at stairways. Minimal dust in living areas.
TheSix·Mar 16, 9:35 AM
Third coat started on main floor today. On track for sanding next week.
TheSix·Mar 18, 3:20 PM

Payment Summary

Outstanding$14,250
Holdback (10%)$4,750