Drywall boarding on 2nd floor — completed 75% of north wall. Found blocking issue at column B4, need additional backing. Notified Mayron for framing correction.
Framing 60% complete on main floor at Sumach. Running ahead of schedule by 1 day. All fire-stopping installed per spec. Cove light profiles started in living area.
Taping first coat completed on main level — Golf Ave. Compound curing well, will sand tomorrow AM. 3 boxes of compound remaining, need to order more from Tapers United.
Spray foam application on basement walls complete — Heathdale. 8 drums of Huntsman chemical used. Waiting on inspection for closed-cell thickness. Upstairs prep starting tomorrow.
Material delivery from PBS Building Supply — 320 sheets 1/2" drywall + corner bead. All received and staged on 2nd floor. Forklift used, no damage.