Daily Logs

/Overview
AN
Daily Logs
March 19, 2026
WS
William Simoes4:42 PM

Drywall boarding on 2nd floor — completed 75% of north wall. Found blocking issue at column B4, need additional backing. Notified Mayron for framing correction.

BoardingIssue
2 photos attached
MF
Mayron Fialho3:10 PM

Framing 60% complete on main floor at Sumach. Running ahead of schedule by 1 day. All fire-stopping installed per spec. Cove light profiles started in living area.

FramingOn Track
GB
Gabriel Belmudes1:45 PM

Taping first coat completed on main level — Golf Ave. Compound curing well, will sand tomorrow AM. 3 boxes of compound remaining, need to order more from Tapers United.

TapingMaterials
JC
Julio Coronado11:20 AM

Spray foam application on basement walls complete — Heathdale. 8 drums of Huntsman chemical used. Waiting on inspection for closed-cell thickness. Upstairs prep starting tomorrow.

MaterialsOn Track
3 photos attached
PH
Pedro Herrera9:30 AM

Material delivery from PBS Building Supply — 320 sheets 1/2" drywall + corner bead. All received and staged on 2nd floor. Forklift used, no damage.

DeliveryMaterials
1 photos attached